Water System Upgrades

Water Bond Improvement Project List:


  

PROJECT UPDATES (week of 3-27-17):

 
    Jackson Oaks, Main Avenue and Boys Ranch Wells Projects: Production wells are constructed. Designs at 100% completion. Out to bid in March 2017 with construction starting in May/June 2017.
      Oak Canyon Booster Station Project: 90% complete, installing new pumps and electronics. Waiting for PG&E to energize new building. Project Photos   Schedule, plans.
     East Dunne Avenue Water Reservoir Project: Design 85% complete. Environmental studies almost complete.
     East Dunne Avenue Booster Station Project: Design 50% complete.
 


Community Meetings:


Jackson Oaks Presentation Slides 8-25-2015
 Jackson Oaks/Holiday Lake Presentation 3-29-16